Please be advised that contractors will be mobilizing Monday morning-February 6th around 8:00 AM to start milling and overlay of new asphalt work on the roads in the attached maps.

1. Work on E 77th Pl and N 126th E Ave will begin Monday-the 6th and should be completed by Wednesday evening. https://ok-owasso.civicplus.com/Document…

2. Work on N 124th E Ave by Mills Elementary School will begin Thursday-the 9th but just on the side roads, milling on N 124th which is by the school will begin Friday around 9:00 AM to not interfere with school drop off; contractors should be done by time for school pickup. ** Asphalt work will be done on Saturday.**
https://ok-owasso.civicplus.com/Document…

Drivers should be aware that there will be 2 in bumps in the street after milling takes place and before the new asphalt is applied. Additionally, residents will not be able to drive on new asphalt until the road is opened by the contractor (est. 2-4 hours).

If you have any questions contact Public Works representative, Brandon Hancock, at 918-693-0373.