Public Meeting Notice
When: September 19th, 2019
Time: 6-7 pm
Where: City Hall, 200 South Main Street (Community Room)
09/12/2019 – Residents in Fairways III, Caudle Estates and El Rio Vista are encouraged to attend a public meeting to discuss a drainage project scheduled to begin on September 23rd.
The project is scheduled to be completed by March of 2020. East 96th Street will remain open except for a scheduled 30 day shutdown which will be announced. The closure will be between North 111th East Avenue and North 109th East Avenue, at which time traffic will be detoured into and out of El Rio Vista. Residents in Caudle will be able to enter and leave their neighborhood at all times.
Please attend if you have questions or concerns.